Want to be in the loop?
subscribe to
our notification
Business News
SOLAR DATA SCRUTINY THE LATEST PAIN POINT FOR PDP PROGRESS
The country’s Power Development Plan VIII is now roughly three years behind schedule and way off the prime minister’s demand that “preparation must be one step ahead” because of disparities in solar power statistics.
Last week, at the demand of Deputy Prime Minister Tran Hong Ha, the Ministry of Industry and Trade (MoIT) was requested to explain the accuracy of solar power statistics in the national Power Development Plan VIII (PDP8) for this decade. The MoIT has drafted the PDP8 six times thus far.
Ha also requested that the MoIT again explain the shift from PDP7 to PDP8, with the emphasis on solar and wind power, owing to discrepancies between the MoIT and Government Inspectorate data.
Prior to mid-2022, the inspectorate looked at the adoption of renewable energy power projects in the amended PDP7, with a particular emphasis on solar energy. According to the MoIT, the inspector general believes that only completed projects with undetermined power rates, projects with signed contracts for equipment procurement, and projects under construction with a total capacity of approximately 636MW should be included in the PDP8.
Approximately 30 meetings have been held to discuss and make comments on the draft PDP8 under the leadership of Le Van Thanh, another DPM. The draft PDP8 has been twice accepted by the National Appraisal Council, but the prime minister has not yet authorised it.
In the draft PDP8 that was submitted to the government in 2021, solar power capacity will remain at 8,736MW towards 2030. A number of projects already included in the revised PDP7, totalling approximately 6,200MW, will be delayed until after 2030.
However, at the end of May 2022, the MoIT requested guidance from the government on how to address the total number of solar power projects that have to be postponed until then. These are projects included in planning, approved for investment, or included in planning but not yet approved for funding, with a combined capacity of approximately 4,100MW.
This proposal differs from previous reports, and the prime minister requested the MoIT’s viewpoint on the direction of processing.
In an explanation provided to the prime minister in July last year, the MoIT recommended deploying about 2,428MW for commercial operation until 2030. With an estimated total investment of around $500 million, the projects or portions of solar power plants whose development has been completed amount to over 450MW. There are about 1,980MW of projects that have been designed and authorised by investors but have yet to be implemented.
The MoIT indicated that the rationale for proposing to continue developing the aforementioned projects is to “avoid legal concerns, litigation, and compensation for investors”. If these projects are authorised by the prime minister and permitted to continue deployment, the system’s total power capacity would reach about 133,900MW by 2030 under the basic plan and 148,350MW under a high-load scenario.
Now, the MoIT wants to continue developing solar power projects with a total capacity of over 4,136MW that are now in the planning stages but have not yet been authorised by investors. These projects are expected to be in the planning stages until 2030.
These projects, according to the ministry, if implemented by 2030, would raise the proportion of renewable energy in the grid by nearly 26 per cent. This impacts the safety and reliability of the power system as well as the economic functioning of existing hydroelectric, thermal, and gas resources.
In March 2021, the MoIT first presented the draft PDP8 to the prime minister. Nevertheless, the calculated plan at the time was not accepted due to deficiencies in the size of power source growth, the structure of power sources, and the illogical regional balance. This results in substantial interregional transmission grid investment.
The plan was confronted with the greatest difficulty of guaranteeing energy supply security and providing sufficient electricity to fulfil the needs of socioeconomic development while improving its quality.
Minister of Industry and Trade Nguyen Hong Dien said during a private session of the National Assembly in October 2022 that the PDP8 is sluggish in terms of the move towards sustainable energy sources.
Minister Dien, who has presented a PDP8 draft to the government three times, said, “Constructing a PDP8 is like painting over an existing artwork. It has to reconcile the organisation of power sources with the framework of regions and provide coordination between supply, distribution, and planning.”
Vietnam hopes to achieve industrialisation by 2030. The MoIT predicts the 2030 electricity demand under three scenarios that correspond to each period’s GDP growth.
The MoIT recommends that the PDP8 performs under a high-load scenario with a stockpile of 15 per cent of the power capacity if the growth in large-capacity power sources falls short of the plan by only 85 per cent. This means that the electricity load will increase by 9.84 per cent per year from 2021 to 2025, which corresponds to a GDP growth rate of 7.5 per cent per year from 2021 to 2025 and 8.88 per cent per year from 2026 to 2030, with a GDP growth rate of 7.2 per cent per year from 2026 to 2030.
The installed output of power plants under this option will reach 145,930MW by 2030, exclusive of solar energy and co-generation sources.
According to data compiled by MoIT, 175 solar power projects with a combined capacity of 15,300MW have been approved and are undergoing planning. At the end of 2020, 131 projects with a total capacity of 8,735MW were in operation.
Source: VIR
Related News
REMITTANCES TO HCM CITY RISE NEARLY 40% IN Q3
Remittances to HCM City reached more than US$2.83 billion in the third quarter of this year, up 39.5 per cent from the previous quarter and 3.6 per cent year-on-year. This was the first quarter showing positive annual growth this year, helping narrow the decline in remittance inflows over the first nine months. According to the State Bank of Vietnam (SBV)’s Regional Branch 2, remittances transferred to HCM City through credit institutions and economic organisations totalled $2.835 billion in Q3, an increase of more than $802 million from the previous quarter.
TECH SECTOR GROWTH OPENS UP OPPORTUNITIES FOR VIỆT NAM TO GO GLOBAL
The growth of the electronics, semiconductor and high-tech sectors worldwide is opening up a variety of opportunities for Vietnamese enterprises to integrate more deeply into the global supply chain. However, to become suppliers for these corporations, domestic enterprises must meet rigorous standards regarding quality, technology, productivity and order fulfilment capabilities.
FOREIGN INVESTORS SEEKING A SYNCHRONISED MANUFACTURING ECOSYSTEM
Instead of focusing only on land costs and incentives as usual, foreign investors are seeking a synchronised manufacturing ecosystem, from stable power supply and logistics to shared infrastructure and the convenience of completing residence procedures for experts to serve their long-term investment in the country.
SENTRYSAFE FHW40200 – PROTECT YOUR VALUABLES, ENJOY PEACE OF MIND!
Looking for a reliable solution to protect your important documents, cash, and valuables from fire and water damage? Genuine SENTRYSAFE - Reliable protection for your valuables and peace of mind! Contact Sen Wai Vietnam for more information and personalized product recommendations.
HCM CITY ATTRACTS US$5.7 BILLION INTO EXPORT PROCESSING AND INDUSTRIAL ZONES
HCM City attracted US$5.7 billion in domestic and foreign investment into its export processing and industrial zones during the first nine months of 2026. The figure exceeded the city's full-year target by 31 per cent, highlighting strong momentum in high-quality industrial investment under Resolution No.10-NQ/TW. Total investment reached 131 per cent of the 2026 target of $4.25 billion and represented a 29 per cent increase compared with the same period in 2025, according to the city's Export Processing and Industrial Zones Authority (HEPZA).
DONG THAP PROVINCE STEPS UP INDUSTRIAL EXPANSION AND INFRASTRUCTURE CONNECTIVITY
Accelerating public investment, strengthening inter-regional connectivity, and expanding industrial land are helping Dong Thap efficiently bolster competitiveness and drive economic growth. Following the 2025 merger of the former Dong Thap and Tien Giang provinces, the expanded Dong Thap province in the Mekong Delta faces mounting pressure to accelerate infrastructure development and strengthen connectivity among local economic zones, urban areas, industrial parks (IPs), and production centres.






















