Want to be in the loop?
subscribe to
our notification
Business News
RENEWABLE ENERGY INVESTMENT CHALLENGES IN VIETNAM: RISKS AND DELAYS
Minister of Industry and Trade Nguyen Hong Dien has noted that many investors have neglected procedures and violated regulations in their rush to meet the Feed-in-Tariff deadline.
Vietnam's renewable energy sector is facing significant challenges, leading to concerns among investors and potential risks of bankruptcy. The director of the Legislative Institute, Nguyen Van Hien, highlights the abrupt shifts in renewable energy investment policies as a major contributing factor to these issues.
The consequences include delayed commercial operations, missed opportunities to benefit from favourable feed-in tariff (FiT) rates, and substantial wastage of untapped wind and solar power. Hien warns that this situation could have long-term implications for the investment climate and hinder the inflow of funds into renewable energy projects.
According to Hien, over 4,600 MW of renewable energy from various projects remains unexploited due to the delayed implementation of FiT rates. Meanwhile, Vietnam faces a power shortage and is forced to rely on electricity imports from other countries.
Acknowledging the inefficiency resulting from under-utilised investment projects, Minister of Industry and Trade Nguyen Hong Dien said that most investors rushed to meet the FiT deadline, neglecting procedures and violating the legal framework. Dien emphasises the need for authorities, investors, and ministries at all levels to collaborate in resolving these issues.
According to local media, the MoIT reveals that many renewable energy project investors violated legal regulations concerning planning, land, and construction investment, resulting in their failure to fulfill legal procedures.
Despite being required to supplement their documentation since late March, these investors have been unable to do so even after two months, preventing them from negotiating prices with Vietnam Electricity (EVN), the state-owned power company.
Furthermore, many investors have not completed the necessary legal documentation to obtain electricity operation permits for their projects. These permits, as per the Electricity Law, are crucial for ensuring the effective utilisation of power projects. The delay in preparing and submitting documents to the relevant authorities has contributed to the overall sluggishness in the sector.
The MoIT also highlights the challenges posed by the instability of wind and solar power, primarily concentrated in the Central region with low-power demand. Developing these renewable energy sources requires substantial investments in transmission lines and storage systems. Moreover, a stable power source capable of continuous generation is necessary to compensate for the intermittent nature of wind and solar power.
Vietnam heavily relies on hydropower, coal, oil, gas, and biomass, while many countries have incorporated nuclear power as a reliable energy source. Despite the higher costs and increased carbon emissions associated with conventional energy sources, Vietnam continues to utilise them to ensure the reliability of its power system.
Minister Dien said that the validity period of FiT rates was explicitly stated in the Prime Minister's decision and should not be abruptly terminated. Projects that fail to commence commercial operations before the deadline cannot benefit from FiT rates and must negotiate prices to share risks and align the interests of the state, businesses, and the public.
Dien emphasised that the cost of renewable energy depends on equipment, technology, and an average annual price reduction of 6-8 per cent. He believes that renewable energy can be the most cost-effective source of electricity, excluding transmission and storage costs.
The pricing framework for electricity issued by the MoIT is based on the Electricity Law, the Price Law, and extensive consultations with international organisations, as well as statistical data from existing solar and wind power plants.
In Vietnam, the preferential pricing framework implemented in 2020 (FiT 2) reduced prices by 8 per cent compared to the 2017 preferential rates (FiT 1), with a further decrease of approximately 7.3 per cent compared to FiT 2.
Currently, it is estimated that 85 renewable energy plants with a total capacity of over 4,730 MW do not meet the requirements to benefit from FiT rates. By the end of May 2023, 59 of these plants, with a capacity of 3,389 MW, have submitted documents to EVN.
Among them, 50 projects have proposed temporary prices equal to half of the pricing framework, ranging from VND 754-908 per kilowatt-hour (excluding VAT), depending on the type of solar or wind energy.
However, several projects are not willing to negotiate within the ministry's pricing framework due to incomplete legal procedures and transmission difficulties.
As of May 31, updated data from EVN reveals that nine transitional renewable energy projects have submitted documents for Commercial Operation Date certification, a prerequisite for grid connection. Seven of these projects, with a total capacity of over 430 MW, have already started generating electricity, effectively doubling the operational capacity within two days.
The MoIT has approved provisional prices for an additional 40 projects, highlighting efforts to address the challenges faced by the renewable energy sector in Vietnam.
Source: VIR
Related News
VIETNAM EXPANDS INLAND CONTAINER DEPOT NETWORK TO 19
The two newly added ICDs are Cai Mep in HCMC and Tan Cang-Moc Bai (phase one) in Tay Ninh Province. Cai Mep ICD, located in Cai Mep Industrial Park in Tan Phuoc Ward, HCMC and developed by Cai Mep International Logistics JSC, covers 9.15 hectares and has an annual handling capacity of about 133,000 TEUs, according to the Government news site (baochinhphu.vn).
HCMC CREDIT UP 1.5% IN Q1
Outstanding loans in the city reached an estimated VND5.28 quadrillion, up 0.77% from the previous month and 16.25% year-on-year, data from the State Bank of Vietnam’s Regional Branch 2 showed. Vietnam dong loans accounted for 96.1% of total credit and rose 1.46% from the end of 2025. Medium- and long-term lending made up 55% of total outstanding loans and increased 3.22%.
HCMC TO ESTABLISH CULTURAL INDUSTRY DEVELOPMENT FUND
The HCMC People’s Committee has tasked relevant departments with establishing a cultural industry development fund and developing a 150-hectare film studio complex. The move follows an instruction by HCMC Party Committee Secretary Tran Luu Quang. The city’s cultural industry development fund will be structured under a venture capital model.
EMPLOYEES’ AVERAGE INCOME INCREASES
Average monthly income of workers in the first quarter reached VND9 million, up 3.8% from the previous quarter and 8.5% from a year earlier, according to the National Statistics Office. Male workers earned an average of VND10.1 million per month, compared with VND7.7 million for female workers. In urban areas, average income reached VND10.7 million per month, while in rural areas it was VND7.9 million.
HCMC KICKS OFF OVER 10 PROJECTS DURING APRIL
Work will start on major projects in transportation, urban development and logistics sectors in HCMC this month, coinciding with Vietnam’s Reunification Day, April 30. They include the N3 ramp at the An Phu interchange with an investment of VND3.4 trillion and the 1.69-hectare Tan Chanh Hiep Park. In addition to these, seven other projects are slated to break ground within the month, including the Ho Tram – Long Thanh airport urban expressway, the Nha Rong – Khanh Hoi port area and the Ho Chi Minh Museum expansion.
VIETNAM’S Q1 FOREIGN TOURIST ARRIVALS HIT RECORD HIGH
Vietnam welcomed nearly 2.1 million international visitors in March, bringing first quarter foreign tourist arrivals to 6.76 million, up 12.4% year-on-year and marking a record high for the period, the national authority for tourism said. Air travel accounted for 82.3% of international arrivals, followed by land at 15.5% and sea at 2.2%, according to the Vietnam National Authority of Tourism.
























