KEY PROJECTS TO CLEAR CONGESTION ON ROADS LEADING TO PORTS IN HCM CITY
The HCM City Department of Transport has asked the city government to give priority in the next five years to six key transport projects worth VNĐ27.488 trillion (US$1.19 billion) in order to clear congestion on roads leading to ports, especially Cát Lái Port in District 2.
Under the public investment plan for the 2021-2025 period, of the six projects, three are being developed, including the Mỹ Thủy intersection project and the other two under the Ring Road 2 project.
The three newly proposed projects would include one to build a six-lane 6.7km-long and 60-metre wide North - South road (section from Nguyễn Văn Linh Road - Bà Chiêm Bridge), with total investment of VNĐ7.013 trillion.
The other two include a project to build the eastern belt route from Phú Mỹ bridge to Mỹ Thủy intersection (in Thủ Đức new City), with an investment of more than VNĐ1.2 trillion.
Another project involves building an eastern ring road from Mỹ Thủy intersection to Nguyễn Duy Trinh - Ring Road 2 intersection, expected to cost more than VNĐ1 trillion.
These newly proposed projects will improve the connection between the Hiệp Phước Port in Nhà Bè District and Cát Lái Port in District 2.
The department said the city should consider suspending or extending completion of projects that have been approved for 2016-2020 period but are not urgent.
Port congestion
Trần Quang Lâm, director of the Department of Transport, said it was important to address the traffic jams on roads leading to Cát Lái Port in District 2, especially Nguyễn Thị Định Street and the Mỹ Thủy intersection.
The city’s seaports extend through districts 2, 4, 7, 9 and Nhà Bè, he said.
Most roads connected to Cát Lái and Hiệp Phước ports are seriously overloaded, including Nguyễn Thị Định, Nguyễn Duy Trinh and Nguyễn Hữu Thọ roads, he added.
Ports located in the city centre, such as Cát Lái, Tân Thuận, Hiệp Phước and Phước Long ports, lack dedicated roads.
Architect Võ Kim Cương, former deputy chief architect of HCM City, said that Hiệp Phước and Cát Lái ports are the city’s largest ports, which face serious congestion. It is important to accelerate the closure of Ring Road 2 to clear congestion near the Cát Lái port area.
Dr Nguyễn Bá Hoàng, vice rector of the HCM City University of Transport, said that rail and water transport connected to the ports should be developed to increase the capacity of freight transport and reduce costs.
It is also vital to close the ring road system and build dedicated railways to Cái Mép and Cát Lái ports.
In a related matter, the city will continue to move its ports to city outskirts to ease congestion on roads as well as build new ones under a national port master plan for 2020-2030.
Cát Lái Port, situated in the eastern gateway, has long been a traffic congestion hotspot with an average of 16,000-17,000 trucks making trips to it daily.
According to the city Maritime Port Administration, between 19,000 and 20,000 trucks each day enter and leave Cát Lái Port through Võ Chí Công, Nguyễn Thị Định and Đồng Văn Cống roads.
There are times when 26,000 vehicles are going in and out the port a day, causing traffic jams in the port area.
Source: VIR
Related News
VIETNAM’S GDP TO GROW 5.5% THIS YEAR – WB
This forecast is based on the assumption of a moderate recovery in manufacturing exports in 2024, fueled by rebound growth of 8.5% year-on-year in the fourth quarter of 2023 and 17.2% year-on-year in the first quarter of 2024, reflecting strengthening global demand, said Dorsati Madani, senior country economist at the WB in Vietnam.
FARE REFUND FOR VISA REJECTION
Cathay Pacific will offer full refunds for cases of visa rejection to provide you with the confidence to explore the world with ease. If you are planning to fly to a destination that requires an entry visa, you can now book with greater peace of mind.
FOUR COMMODITIES POST Q1 EXPORT VALUE OF OVER 5 BILLION USD
The total export turnover of agricultural, forestry, and fisheries products in the first three months of 2024 is estimated to reach 13.53 billion USD, an increase of 21.8% compared to the same period of 2023.
MOIT PROPOSES SCHEME TO BOOST RENEWABLE ENERGY PROCUREMENT
The proposed Direct Power Purchase Agreement (DDPA) mechanism, outlined in the draft decree, targets organisations and individuals consuming electricity from the 22kV power grid or higher, with a monthly consumption averaging 500,000kWh. However, residential households are excluded from direct procurement.
REAL ESTATE BONDS PLACE PRESSURE ON ISSUING FIRMS
The ministry’s recent report underscores concerns within Vietnam’s corporate bond market for 2023 and 2024. It emphasizes the critical need to address hindrances to the real estate sector in line with the objectives provided in Government Resolution No. 33/NQ-CP, which aims to stabilize the industry.
DA NANG CUSTOMS FOCUSES ON DEVELOPING CUSTOMS-BUSINESS PARTNERSHIPS
Da Nang Customs Department issued an action plan for developing customs-business partnership in 2024. One of the new events this year is the workshop on “Settlement reports for enterprises engaged in outsourcing, export production and export processing” held in Da Nang Customs Department on April 16, 2024.